Conclusions

The project successfully obtained equipment and software for six Shad Valley campuses.

The machines arrived too late for maximum benefit. This was due primarily to delayed contact with the appropriate people at each program and to delays from the co-ordinator.

A late-breaking discovery hindered the effort to deliver SGI machines and limited us to only six.

Session organizers did not have enough time beforehand to prepare workshops using the SGIs to maximum benefit, or to become sufficiently familiar with Alias software for maximum benefit.

The suggested national network and teleconference were not achieved.